Land use, zoning, and rezoning attorneys for Johns Creek owners, developers, and neighbors

Johns Creek runs rezonings on a monthly cycle: file by the first Tuesday, present at a Public Participation Meeting, go before the Planning Commission on the next first Tuesday, and finish at the Mayor and Council, roughly three to four months end to end. Miles Hansford keeps applications on that cycle.

Johns Creek's Zoning Ordinance, Appendix A of the city code, governs rezonings, special use permits, and variances through the Community Development Department at 11360 Lakefield Drive. The city is in the middle of its largest land use shift since incorporation: the 192-acre Town Center and the 43-acre Medley project are giving Johns Creek a downtown. Restaurants opening there also need a license; see our Johns Creek alcohol licensing page.

1st TuesdayMonthly filing deadline and Planning Commission hearing night, 7 p.m.
3–4 monthsCity's stated rezoning timeline from filing to Council decision
30 daysDeadline to challenge a zoning decision under O.C.G.A. § 36-66-5.1

What we do in Johns Creek

  • Rezonings (RZ), special use permits (SUP), and concurrent variances (VC)
  • Pre-application meetings, letters of intent, and conceptual site plans
  • Public Participation Meetings and neighbor outreach
  • Board of Zoning Appeals hearings
  • Representation of neighbors and HOAs opposing a rezoning
  • Petitions for review and declaratory actions in Fulton County Superior Court

A Monthly Cycle

Miss the first-Tuesday deadline and you lose a month. We manage the pre-application meeting, the filing, and the hearings so the application keeps moving.

Public Participation Meeting

Johns Creek puts residents in a room with your site plan before any hearing. We prepare the presentation and turn objections into conditions you can live with.

Town Center & Redevelopment

Medley, Town Center, and Medlock Crossing are reshaping Medlock Bridge Road. We handle the entitlements for projects in and around the new district.

Miles Hansford attorney reviewing a Johns Creek, Georgia rezoning site plan
Johns Creek Zoning Ordinance, Appendix A, Article XXVIII
How Johns Creek Handles Zoning

Pre-application, first-Tuesday filing, a neighborhood meeting, and two hearings

Community Development's Planning & Zoning division administers the Zoning Ordinance. Every rezoning, special use permit, or variance begins with a mandatory pre-application meeting where staff review a conceptual site plan, a letter of intent, and the pre-application form. Applications are due the first Tuesday of each month. Residents then get an informal Public Participation Meeting, typically the first Thursday at 7 p.m. in Council Chambers, to review site plans and renderings before any formal hearing.

The seven-member Planning Commission, a recommending body, hears rezonings, variances, special use permits, and ordinance amendments on the first Tuesday at 7 p.m. The Mayor and City Council make the final decision. The Board of Zoning Appeals meets the third Tuesday at 7 p.m. The city describes the full process as approximately three months on its FAQ page and a four-month review timeline on its Planning Commission page. Fees, sign posting, and mailed-notice details change; confirm current requirements with the firm.

  • Rezonings and zoning condition amendments
  • Special use permits and concurrent variances
  • Variances and administrative appeals
  • Text amendments and comprehensive plan questions
  • Opposition strategy for neighbors and HOAs
What We Handle

Johns Creek land use and zoning services

Each stage of the monthly cycle, and the appeal if it comes to that.

Pre-application preparation

Conceptual site plan, letter of intent, and pre-application form, tested against the ordinance before the staff meeting.

Rezonings and special use permits

The full first-Tuesday cycle through the Planning Commission and Council. See our rezoning practice.

Public Participation Meetings

Presentation, neighbor response, and the record of outreach that the Planning Commission expects to see.

Variances and BZA matters

Hardship variances and administrative appeals before the body the ordinance directs, with a record built for review.

Redevelopment entitlements

Mixed-use, retail, and residential projects in and around Town Center, Medley, and Medlock Crossing.

Opposition and appeals

Neighbors and HOAs at every stage, and petitions for review or declaratory actions within 30 days.

Key Facts

Johns Creek zoning at a glance

From the City of Johns Creek's Planning & Zoning FAQ, Planning Commission, and public participation pages; fees and notice periods should be confirmed with the firm.

Zoning authority
Community Development, Planning & Zoning, 11360 Lakefield Drive, Johns Creek, GA 30097; 678-512-3200. Mandatory pre-application meeting.
Recommending body
Planning Commission, seven members, first Tuesday at 7 p.m., Council Chambers.
Deciding body
Mayor and City Council.
Code
Zoning Ordinance, Appendix A of the Code of Ordinances; Article XXVIII, Rezoning and Other Amendment Procedures.
Comprehensive plan
The city's current plan and any rewrite status: confirm with the firm.
Public notice & signs
O.C.G.A. § 36-66-4: newspaper notice 15 to 45 days before the hearing and a sign posted at least 15 days before. City-specific posting details: confirm with the firm.
Neighborhood meeting
Public Participation Meeting, typically first Thursday at 7 p.m., Council Chambers, before the Planning Commission hearing.
Typical timeline
Approximately three to four months; filing deadline first Tuesday of each month.
Variances & appeals body
Board of Zoning Appeals, third Tuesday at 7 p.m.
Appeal deadline
30 days from the written decision, Fulton County Superior Court, O.C.G.A. § 36-66-5.1.

Sources: City of Johns Creek Planning & Zoning FAQ, Planning Commission, Zoning Public Participation Meetings, and Major Redevelopment Projects pages; Johns Creek Zoning Ordinance (Appendix A); O.C.G.A. § 36-66-4 and § 36-66-5.1.

In Depth

Rezoning in Johns Creek: cycle, criteria, and the new downtown

What to expect from filing to final decision.

The monthly cycle step by step

Johns Creek's process is unusually predictable. First, a mandatory pre-application meeting with Planning & Zoning staff, bringing a conceptual site plan, a letter of intent, and the pre-application form. Second, filing by the first Tuesday of the month. Third, an informal Public Participation Meeting, typically the first Thursday at 7 p.m. in Council Chambers, where residents review site plans and renderings. Fourth, the Planning Commission public hearing on a first Tuesday at 7 p.m., producing a recommendation. Fifth, the Mayor and Council hearing and vote, often with conditions. Georgia law requires newspaper notice 15 to 45 days before the hearing and a sign on the property at least 15 days before.

Special use permits, variances, and the plan

The Planning Commission hears three application types: rezonings (RZ), variances (VC), and special use permits (SUP). Special use permits and variances are quasi-judicial and reviewed by a court on the record, so expert reports and testimony belong at the hearing. The Board of Zoning Appeals meets the third Tuesday at 7 p.m.; we confirm which body will hear a particular variance or appeal before filing.

Georgia courts expect rezonings to be consistent with the comprehensive plan and future land use map. If the request conflicts with the plan, a plan amendment may be needed first, which adds a cycle. We check plan consistency at the pre-application stage.

Town Center, Medley, and Medlock Bridge Road

Johns Creek's 192-acre Town Center along Medlock Bridge Road, McGinnis Ferry Road, and Johns Creek Parkway includes a 40-acre retail and mixed-use district and Creekside Park. Within it, the 43-acre Medley project brings 164,000 square feet of retail, roughly 900 residences, a 150-key boutique hotel planned for 2028, and a Boehringer Ingelheim office. The Council approved a $305,000 engineering contract in February 2023 for a pedestrian tunnel under GA 141 connecting Town Center to the west-side retail, and the 21-acre Medlock Crossing center is being marketed for mixed-use redevelopment. Parcels near these projects will see rezoning pressure and neighbor scrutiny in equal measure.

Opposing a rezoning and appealing a decision

Neighbors have the Public Participation Meeting, the Planning Commission hearing, and the Council hearing. The most effective opposition is specific and documented: plan conflicts, traffic data, and any notice defect under O.C.G.A. § 36-66-4. To sue, a neighbor must show special damage beyond that of similarly situated owners.

Under O.C.G.A. § 36-66-5.1 any challenge must be filed within 30 days of the written decision in Fulton County Superior Court. Constitutional challenges to a legislative rezoning are heard de novo, with the owner required to prove by clear and convincing evidence a significant detriment and no substantial relation to the public welfare. Special use permits, variances, and administrative appeals are reviewed on the record by petition for review under O.C.G.A. § 5-3-1.

Why Miles Hansford

Land use counsel minutes from Johns Creek City Hall

Miles Hansford is based at 1725 Windward Concourse in Alpharetta, minutes from Johns Creek City Hall. Partner David Davidson leads the firm's Land Use & Zoning practice, and the firm's land use and zoning practice covers rezonings, special use permits, variances, and appeals across North Fulton, Forsyth, and Gwinnett counties.

Johns Creek's monthly cycle rewards applicants who arrive prepared and punishes those who miss a Tuesday. We run the calendar so the project does not lose a month.

Miles Hansford Law Firm attorneys in Alpharetta, Georgia, near Johns Creek
What to Expect

How a Johns Creek zoning matter proceeds

Four stages on a monthly cycle.

1

Feasibility

Zoning district, comprehensive plan, and the likely conditions, before you contract.

2

Pre-application and filing

The staff meeting, then a complete application by the first Tuesday.

3

Meeting and hearings

Public Participation Meeting, Planning Commission, and Council.

4

Conditions or appeal

Negotiated conditions, or a petition or declaratory action within 30 days.

Frequently Asked Questions

Johns Creek zoning and rezoning questions

How long does a rezoning take in Johns Creek?

The city describes the process as approximately three months on its Planning & Zoning FAQ and as a four-month review timeline on its Planning Commission page. Applications are due the first Tuesday of each month, and the Planning Commission hears them on a first Tuesday at 7 p.m., so timing the filing matters.

Do I need to meet with the city before filing in Johns Creek?

Yes. A pre-application meeting with Planning & Zoning staff is mandatory. Bring a conceptual site plan, a letter of intent, and the city's pre-application form. Staff use the meeting to flag ordinance and comprehensive plan issues before the first-Tuesday filing.

What is a Public Participation Meeting?

An informal meeting, typically the first Thursday at 7 p.m. in Council Chambers, where residents review the applicant's site plans and renderings before the Planning Commission and Council hearings. It is the applicant's first chance to hear objections and the neighbors' first chance to be heard.

Who makes the final decision on a Johns Creek rezoning?

The Mayor and City Council. The seven-member Planning Commission is a recommending body that hears rezonings, variances, special use permits, and ordinance amendments on the first Tuesday at 7 p.m. in Council Chambers and forwards a recommendation to the Council, which holds its own hearing and votes.

Where do variances go in Johns Creek?

Variances filed with a rezoning (VC) go to the Planning Commission, which recommends to the Mayor and Council. Whether a stand-alone variance or administrative appeal goes there or to the Board of Zoning Appeals, which meets the third Tuesday at 7 p.m., depends on the Zoning Ordinance, so we confirm the path before filing. Variance decisions are quasi-judicial and reviewed on the record.

What is happening at Town Center and Medley?

Town Center is a 192-acre district along Medlock Bridge Road with a 40-acre retail and mixed-use core and Creekside Park. Medley, a 43-acre project inside it, includes 164,000 square feet of retail, about 900 residences, a boutique hotel planned for 2028, and a Boehringer Ingelheim office.

How can neighbors oppose a rezoning in Johns Creek?

Attend the Public Participation Meeting, the Planning Commission hearing, and the Council hearing, and put specific evidence on the record: comprehensive plan conflicts, traffic, and notice defects under O.C.G.A. § 36-66-4. To challenge an approval in court, a neighbor must show special damage and file within 30 days.

How do I appeal a Johns Creek zoning decision?

File in Fulton County Superior Court within 30 days of the written decision under O.C.G.A. § 36-66-5.1. Constitutional challenges to rezonings are heard de novo under a clear-and-convincing standard; special use permits, variances, and administrative appeals are reviewed on the record by petition for review under O.C.G.A. § 5-3-1.

Nearby Jurisdictions

Land use and zoning in nearby North Metro jurisdictions

Johns Creek borders Alpharetta, Forsyth County, and Gwinnett County.

Request a Consultation

Planning a project or facing one in Johns Creek?

Call 770-781-4100 or contact Miles Hansford in Alpharetta. We will review the parcel and get you on the next first-Tuesday cycle.

Miles Hansford Law Firm

Phone: 770-781-4100

Address:
1725 Windward Concourse, Suite 150
Alpharetta, GA 30005

Consultations: Contact the firm online to get started.

This page is for general informational purposes and is not legal advice. Fees, deadlines, and ordinance provisions change; confirm current requirements with the relevant jurisdiction or with the firm. No attorney-client relationship is created by viewing this content or sending a message through the website.